Conclusion Video Conyers Job Progress March 21, 2024

We strive to make sure that on the last day of our job our clients have paid exactly what they were told they were going to pay on the first day of the job and that they are totally satisfied that they hired the right team for the job.

This job was started on January 25th, 2024 and the basic construction, which is the framing, the HVAC, the plumbing, the electrical, the insulation, the drywall and the trim were completed and all passed inspection in less then 4 weeks. The add ons which were the wet bar cabinetry and granite installation, the paint, and the flooring were all completed by March 20th at the costs described in the video below.